Last update at: 2024-10-15T17:00:00+01:00
**Please note that the last update time shown is rounded to the next market interval of 30 minutes
All times are in UTC.
Affected Unit | Affected Unit EIC Code | Market Participant | Market Participant Code | Message ID | Event Status | Type Of Unavailability | Type Of Event | Publication Date | Event Start | Event Stop | Unit of Measurement | Unavailable Capacity | Available Capacity | Installed Capacity | Reason Of Unavailability | Remarks | Fuel Type | Bidding Zone |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
< 29 30 31 32 33 > | ||||||||||||||||||
TAWN1 | 47W000000000214U | SSE Generation Ireland Ltd |
47X0000000000592 | 0000000000000000000008838_004 | Dismissed | Planned | Production unavailability | 2024-07-19T16:48:02+01:00 | 2024-07-08T13:00:00+01:00 | 2024-07-19T19:00:00+01:00 | MW | 52 | 0 | 52 | Foreseen Maintenance | Planned Outage |
Fossil Gas | 10Y1001A1001A59C |
TAWN1 | 47W000000000214U | SSE Generation Ireland Ltd |
47X0000000000592 | 0000000000000000000008838_003 | Dismissed | Planned | Production unavailability | 2024-07-07T10:29:27+01:00 | 2024-07-08T13:00:00+01:00 | 2024-07-19T17:00:00+01:00 | MW | 52 | 0 | 52 | Foreseen Maintenance | Planned Outage |
Fossil Gas | 10Y1001A1001A59C |
TAWN1 | 47W000000000214U | SSE Generation Ireland Ltd |
47X0000000000592 | 0000000000000000000008838_002 | Dismissed | Planned | Production unavailability | 2024-03-27T15:22:28+00:00 | 2024-07-08T09:00:00+01:00 | 2024-07-19T17:00:00+01:00 | MW | 52 | 0 | 52 | Foreseen Maintenance | Planned Outage |
Fossil Gas | 10Y1001A1001A59C |
TAWN1 | 47W000000000214U | SSE Generation Ireland Ltd |
47X0000000000592 | 0000000000000000000008838_001 | Dismissed | Planned | Production unavailability | 2024-02-09T09:42:37+00:00 | 2024-06-29T09:00:00+01:00 | 2024-07-05T17:00:00+01:00 | MW | 52 | 0 | 52 | Foreseen Maintenance | Planned Outage |
Fossil Gas | 10Y1001A1001A59C |
T_KEAD-2 | 48W000000KEAD-23 | KEADBY GEN. LTD |
48X000000000073U | 0000000000000000000009253_002 | Inactive | Planned | Production unavailability | 2024-07-19T19:02:32+01:00 | 2024-07-19T17:00:00+01:00 | 2024-07-19T18:00:00+01:00 | MW | 150 | 690 | 840 | Failure | Weather |
Fossil Gas | 10YGB----------A |
T_KEAD-2 | 48W000000KEAD-23 | KEADBY GEN. LTD |
48X000000000073U | 0000000000000000000009253_001 | Dismissed | Planned | Production unavailability | 2024-07-18T09:00:56+01:00 | 2024-07-19T17:00:00+01:00 | 2024-07-19T18:00:00+01:00 | MW | 150 | 690 | 840 | Failure | Weather |
Fossil Gas | 10YGB----------A |
T_KEAD-2 | 48W000000KEAD-23 | KEADBY GEN. LTD |
48X000000000073U | 0000000000000000000009252_004 | Inactive | Planned | Production unavailability | 2024-07-19T18:02:32+01:00 | 2024-07-19T12:00:00+01:00 | 2024-07-19T17:00:00+01:00 | MW | 100 | 740 | 840 | Failure | Weather |
Fossil Gas | 10YGB----------A |
T_KEAD-2 | 48W000000KEAD-23 | KEADBY GEN. LTD |
48X000000000073U | 0000000000000000000009252_003 | Dismissed | Planned | Production unavailability | 2024-07-18T08:59:54+01:00 | 2024-07-19T12:00:00+01:00 | 2024-07-19T17:00:00+01:00 | MW | 100 | 740 | 840 | Failure | Weather |
Fossil Gas | 10YGB----------A |
T_KEAD-2 | 48W000000KEAD-23 | KEADBY GEN. LTD |
48X000000000073U | 0000000000000000000009252_002 | Dismissed | Planned | Production unavailability | 2024-07-18T08:27:50+01:00 | 2024-07-19T12:00:00+01:00 | 2024-07-19T21:00:00+01:00 | MW | 100 | 740 | 840 | Failure | Weather |
Fossil Gas | 10YGB----------A |
T_KEAD-2 | 48W000000KEAD-23 | KEADBY GEN. LTD |
48X000000000073U | 0000000000000000000009252_001 | Dismissed | Planned | Production unavailability | 2024-07-18T06:36:23+01:00 | 2024-07-19T12:00:00+01:00 | 2024-07-19T21:00:00+01:00 | MW | 152 | 688 | 840 | Failure | Weather |
Fossil Gas | 10YGB----------A |
TAWN3 | 47W000000000215S | SSE Generation Ireland Ltd |
47X0000000000592 | 0000000000000000000008642_005 | Inactive | Planned | Production unavailability | 2024-07-19T15:47:32+01:00 | 2024-07-08T13:00:00+01:00 | 2024-07-19T14:45:00+01:00 | MW | 52 | 0 | 52 | Foreseen Maintenance | Planned Outage |
Fossil Gas | 10Y1001A1001A59C |
TAWN3 | 47W000000000215S | SSE Generation Ireland Ltd |
47X0000000000592 | 0000000000000000000008642_004 | Dismissed | Planned | Production unavailability | 2024-07-19T14:36:01+01:00 | 2024-07-08T13:00:00+01:00 | 2024-07-19T14:45:00+01:00 | MW | 52 | 0 | 52 | Foreseen Maintenance | Planned Outage |
Fossil Gas | 10Y1001A1001A59C |
TAWN3 | 47W000000000215S | SSE Generation Ireland Ltd |
47X0000000000592 | 0000000000000000000008642_003 | Dismissed | Planned | Production unavailability | 2024-07-07T10:27:15+01:00 | 2024-07-08T13:00:00+01:00 | 2024-07-19T17:00:00+01:00 | MW | 52 | 0 | 52 | Foreseen Maintenance | Planned Outage |
Fossil Gas | 10Y1001A1001A59C |
TAWN3 | 47W000000000215S | SSE Generation Ireland Ltd |
47X0000000000592 | 0000000000000000000008642_002 | Dismissed | Planned | Production unavailability | 2024-03-27T15:23:48+00:00 | 2024-07-08T09:00:00+01:00 | 2024-07-19T17:00:00+01:00 | MW | 52 | 0 | 52 | Foreseen Maintenance | Planned Outage |
Fossil Gas | 10Y1001A1001A59C |
TAWN3 | 47W000000000215S | SSE Generation Ireland Ltd |
47X0000000000592 | 0000000000000000000008642_001 | Dismissed | Planned | Production unavailability | 2023-11-27T12:37:44+00:00 | 2024-07-06T09:00:00+01:00 | 2024-07-12T17:00:00+01:00 | MW | 52 | 0 | 52 | Foreseen Maintenance | Planned Outage |
Fossil Gas | 10Y1001A1001A59C |
T_DBAWO-2 | 48W00000DBAWO-2H | Doggerbank Offshore Wind Farm Project 1 Projco Limited |
48X0000000003113 | 0000000000000000000009255_003 | Inactive | Planned | Production unavailability | 2024-07-19T10:17:32+01:00 | 2024-07-17T00:00:00+01:00 | 2024-07-19T09:07:00+01:00 | MW | 0 | 39 | 39 | Shutdown | Commissioning |
Wind Offshore | 10YGB----------A |
T_DBAWO-2 | 48W00000DBAWO-2H | Doggerbank Offshore Wind Farm Project 1 Projco Limited |
48X0000000003113 | 0000000000000000000009255_002 | Dismissed | Planned | Production unavailability | 2024-07-19T08:30:15+01:00 | 2024-07-17T00:00:00+01:00 | 2024-07-19T09:07:00+01:00 | MW | 0 | 39 | 39 | Shutdown | Commissioning |
Wind Offshore | 10YGB----------A |
T_DBAWO-2 | 48W00000DBAWO-2H | Doggerbank Offshore Wind Farm Project 1 Projco Limited |
48X0000000003113 | 0000000000000000000009255_001 | Dismissed | Planned | Production unavailability | 2024-07-18T09:22:35+01:00 | 2024-07-17T00:00:00+01:00 | 2024-07-25T00:00:00+01:00 | MW | 0 | 39 | 39 | Shutdown | Commissioning |
Wind Offshore | 10YGB----------A |
T_MEDP-1 | 48W000000MEDP-12 | MEDWAY POWER LTD |
48X000000000076O | 0000000000000000000009250_003 | Inactive | Planned | Production unavailability | 2024-07-17T22:02:31+01:00 | 2024-07-17T15:30:00+01:00 | 2024-07-17T21:00:00+01:00 | MW | 710 | 0 | 710 | Failure | Plant Fault - Turbine |
Fossil Gas | 10YGB----------A |
T_MEDP-1 | 48W000000MEDP-12 | MEDWAY POWER LTD |
48X000000000076O | 0000000000000000000009250_002 | Dismissed | Planned | Production unavailability | 2024-07-17T20:56:08+01:00 | 2024-07-17T15:30:00+01:00 | 2024-07-17T21:00:00+01:00 | MW | 710 | 0 | 710 | Failure | Plant Fault - Turbine |
Fossil Gas | 10YGB----------A |
T_MEDP-1 | 48W000000MEDP-12 | MEDWAY POWER LTD |
48X000000000076O | 0000000000000000000009250_001 | Dismissed | Planned | Production unavailability | 2024-07-17T15:29:32+01:00 | 2024-07-17T15:30:00+01:00 | 2024-07-19T15:30:00+01:00 | MW | 710 | 0 | 710 | Failure | Plant Fault - Turbine |
Fossil Gas | 10YGB----------A |
T_MEDP-1 | 48W000000MEDP-12 | MEDWAY POWER LTD |
48X000000000076O | 0000000000000000000009248_003 | Inactive | Unplanned | Production unavailability | 2024-07-17T01:02:32+01:00 | 2024-07-15T17:58:00+01:00 | 2024-07-16T23:59:00+01:00 | MW | 400 | 310 | 710 | Failure | Plant Fault - HRSG |
Fossil Gas | 10YGB----------A |
T_MEDP-1 | 48W000000MEDP-12 | MEDWAY POWER LTD |
48X000000000076O | 0000000000000000000009248_002 | Dismissed | Unplanned | Production unavailability | 2024-07-15T22:21:19+01:00 | 2024-07-15T17:58:00+01:00 | 2024-07-16T23:59:00+01:00 | MW | 400 | 310 | 710 | Failure | Plant Fault - HRSG |
Fossil Gas | 10YGB----------A |
T_MEDP-1 | 48W000000MEDP-12 | MEDWAY POWER LTD |
48X000000000076O | 0000000000000000000009248_001 | Dismissed | Unplanned | Production unavailability | 2024-07-15T18:04:49+01:00 | 2024-07-15T17:58:00+01:00 | 2024-07-15T23:59:00+01:00 | MW | 400 | 310 | 710 | Failure | Plant Fault - HRSG |
Fossil Gas | 10YGB----------A |
T_MEDP-1 | 48W000000MEDP-12 | MEDWAY POWER LTD |
48X000000000076O | 0000000000000000000009247_005 | Inactive | Planned | Production unavailability | 2024-07-15T19:02:32+01:00 | 2024-07-15T16:50:00+01:00 | 2024-07-15T17:50:00+01:00 | MW | 50 | 660 | 710 | Foreseen Maintenance | Testing |
Fossil Gas | 10YGB----------A |
T_MEDP-1 | 48W000000MEDP-12 | MEDWAY POWER LTD |
48X000000000076O | 0000000000000000000009247_004 | Dismissed | Planned | Production unavailability | 2024-07-15T16:47:44+01:00 | 2024-07-15T16:50:00+01:00 | 2024-07-15T17:50:00+01:00 | MW | 50 | 660 | 710 | Foreseen Maintenance | Testing |
Fossil Gas | 10YGB----------A |
T_MEDP-1 | 48W000000MEDP-12 | MEDWAY POWER LTD |
48X000000000076O | 0000000000000000000009247_003 | Dismissed | Planned | Production unavailability | 2024-07-15T15:27:36+01:00 | 2024-07-15T15:30:00+01:00 | 2024-07-15T17:30:00+01:00 | MW | 210 | 500 | 710 | Foreseen Maintenance | Testing |
Fossil Gas | 10YGB----------A |
T_MEDP-1 | 48W000000MEDP-12 | MEDWAY POWER LTD |
48X000000000076O | 0000000000000000000009247_002 | Dismissed | Planned | Production unavailability | 2024-07-15T14:28:21+01:00 | 2024-07-15T14:00:00+01:00 | 2024-07-15T16:00:00+01:00 | MW | 410 | 300 | 710 | Foreseen Maintenance | Testing |
Fossil Gas | 10YGB----------A |
T_MEDP-1 | 48W000000MEDP-12 | MEDWAY POWER LTD |
48X000000000076O | 0000000000000000000009247_001 | Dismissed | Planned | Production unavailability | 2024-07-15T12:20:10+01:00 | 2024-07-15T13:00:00+01:00 | 2024-07-15T15:00:00+01:00 | MW | 510 | 200 | 710 | Foreseen Maintenance | Testing |
Fossil Gas | 10YGB----------A |
T_GLNDO-1 | 48W00000GLNDO-1G | SSE GENERATION |
48X000000000077M | 0000000000000000000008813_002 | Dismissed | Planned | Production unavailability | 2024-07-15T14:18:55+01:00 | 2024-07-30T09:00:00+01:00 | 2024-07-30T16:00:00+01:00 | MW | 100 | 0 | 100 | Foreseen Maintenance | Planned Outage |
Hydro Water Reservoir | 10YGB----------A |
T_GLNDO-1 | 48W00000GLNDO-1G | SSE GENERATION |
48X000000000077M | 0000000000000000000008813_001 | Dismissed | Planned | Production unavailability | 2024-01-29T08:51:26+00:00 | 2024-07-30T09:00:00+01:00 | 2024-07-30T16:00:00+01:00 | MW | 100 | 0 | 100 | Foreseen Maintenance | Planned Outage |
Hydro Water Reservoir | 10YGB----------A |
T_MEDP-1 | 48W000000MEDP-12 | MEDWAY POWER LTD |
48X000000000076O | 0000000000000000000009240_002 | Inactive | Planned | Production unavailability | 2024-07-15T14:02:31+01:00 | 2024-07-15T02:01:00+01:00 | 2024-07-15T13:00:00+01:00 | MW | 610 | 100 | 710 | Foreseen Maintenance | Testing |
Fossil Gas | 10YGB----------A |
T_MEDP-1 | 48W000000MEDP-12 | MEDWAY POWER LTD |
48X000000000076O | 0000000000000000000009240_001 | Dismissed | Planned | Production unavailability | 2024-07-12T10:00:41+01:00 | 2024-07-15T02:01:00+01:00 | 2024-07-15T13:00:00+01:00 | MW | 610 | 100 | 710 | Foreseen Maintenance | Testing |
Fossil Gas | 10YGB----------A |
T_MEDP-1 | 48W000000MEDP-12 | MEDWAY POWER LTD |
48X000000000076O | 0000000000000000000009234_002 | Inactive | Planned | Production unavailability | 2024-07-15T03:02:32+01:00 | 2024-07-12T12:00:00+01:00 | 2024-07-15T02:00:00+01:00 | MW | 710 | 0 | 710 | Foreseen Maintenance | Testing |
Fossil Gas | 10YGB----------A |
T_MEDP-1 | 48W000000MEDP-12 | MEDWAY POWER LTD |
48X000000000076O | 0000000000000000000009234_001 | Dismissed | Planned | Production unavailability | 2024-07-09T15:30:02+01:00 | 2024-07-12T12:00:00+01:00 | 2024-07-15T02:00:00+01:00 | MW | 710 | 0 | 710 | Foreseen Maintenance | Testing |
Fossil Gas | 10YGB----------A |
T_VKNGW-2 | 48W00000VKNGW-22 | Viking Energy Wind Farm LLP |
48X000000000314Y | 0000000000000000000009244_002 | Inactive | Planned | Production unavailability | 2024-07-13T12:02:32+01:00 | 2024-07-13T10:00:00+01:00 | 2024-07-13T11:00:00+01:00 | MW | 112 | 0 | 112 | Foreseen Maintenance | Grid |
Wind Onshore | 10YGB----------A |
T_VKNGW-3 | 48W00000VKNGW-30 | Viking Energy Wind Farm LLP |
48X000000000314Y | 0000000000000000000009246_002 | Inactive | Planned | Production unavailability | 2024-07-13T12:02:32+01:00 | 2024-07-13T10:00:00+01:00 | 2024-07-13T11:00:00+01:00 | MW | 108 | 0 | 108 | Foreseen Maintenance | Grid |
Wind Onshore | 10YGB----------A |
T_VKNGW-1 | 48W00000VKNGW-14 | Viking Energy Wind Farm LLP |
48X000000000314Y | 0000000000000000000009243_002 | Inactive | Unplanned | Production unavailability | 2024-07-13T12:02:32+01:00 | 2024-07-13T10:00:00+01:00 | 2024-07-13T11:00:00+01:00 | MW | 112 | 0 | 112 | Foreseen Maintenance | Grid |
Wind Onshore | 10YGB----------A |
T_VKNGW-1 | 48W00000VKNGW-14 | Viking Energy Wind Farm LLP |
48X000000000314Y | 0000000000000000000009243_001 | Dismissed | Unplanned | Production unavailability | 2024-07-13T10:08:55+01:00 | 2024-07-13T10:00:00+01:00 | 2024-07-13T11:00:00+01:00 | MW | 112 | 0 | 112 | Foreseen Maintenance | Grid |
Wind Onshore | 10YGB----------A |
T_VKNGW-2 | 48W00000VKNGW-22 | Viking Energy Wind Farm LLP |
48X000000000314Y | 0000000000000000000009244_001 | Dismissed | Planned | Production unavailability | 2024-07-13T10:11:12+01:00 | 2024-07-13T10:00:00+01:00 | 2024-07-13T11:00:00+01:00 | MW | 112 | 0 | 112 | Foreseen Maintenance | Grid |
Wind Onshore | 10YGB----------A |
T_VKNGW-3 | 48W00000VKNGW-30 | Viking Energy Wind Farm LLP |
48X000000000314Y | 0000000000000000000009246_001 | Dismissed | Planned | Production unavailability | 2024-07-13T10:17:05+01:00 | 2024-07-13T10:00:00+01:00 | 2024-07-13T11:00:00+01:00 | MW | 108 | 0 | 108 | Foreseen Maintenance | Grid |
Wind Onshore | 10YGB----------A |
T_VKNGW-4 | 48W00000VKNGW-4Z | Viking Energy Wind Farm LLP |
48X000000000314Y | 0000000000000000000009208_017 | Inactive | Planned | Production unavailability | 2024-07-13T11:47:32+01:00 | 2024-07-09T10:00:00+01:00 | 2024-07-13T10:45:00+01:00 | MW | 112 | 0 | 112 | Foreseen Maintenance | Grid |
Wind Onshore | 10YGB----------A |
T_VKNGW-4 | 48W00000VKNGW-4Z | Viking Energy Wind Farm LLP |
48X000000000314Y | 0000000000000000000009208_016 | Dismissed | Planned | Production unavailability | 2024-07-13T10:44:23+01:00 | 2024-07-09T10:00:00+01:00 | 2024-07-13T10:45:00+01:00 | MW | 112 | 0 | 112 | Foreseen Maintenance | Grid |
Wind Onshore | 10YGB----------A |
T_VKNGW-4 | 48W00000VKNGW-4Z | Viking Energy Wind Farm LLP |
48X000000000314Y | 0000000000000000000009208_015 | Dismissed | Planned | Production unavailability | 2024-07-13T10:19:54+01:00 | 2024-07-09T10:00:00+01:00 | 2024-07-13T11:00:00+01:00 | MW | 112 | 0 | 112 | Foreseen Maintenance | Grid |
Wind Onshore | 10YGB----------A |
T_VKNGW-4 | 48W00000VKNGW-4Z | Viking Energy Wind Farm LLP |
48X000000000314Y | 0000000000000000000009208_014 | Dismissed | Planned | Production unavailability | 2024-07-13T10:04:48+01:00 | 2024-07-09T10:00:00+01:00 | 2024-08-13T11:00:00+01:00 | MW | 112 | 0 | 112 | Foreseen Maintenance | Grid |
Wind Onshore | 10YGB----------A |
T_VKNGW-4 | 48W00000VKNGW-4Z | Viking Energy Wind Farm LLP |
48X000000000314Y | 0000000000000000000009208_013 | Dismissed | Planned | Production unavailability | 2024-07-12T16:58:38+01:00 | 2024-07-09T10:00:00+01:00 | 2024-08-13T09:00:00+01:00 | MW | 112 | 0 | 112 | Foreseen Maintenance | Grid |
Wind Onshore | 10YGB----------A |
T_VKNGW-4 | 48W00000VKNGW-4Z | Viking Energy Wind Farm LLP |
48X000000000314Y | 0000000000000000000009208_012 | Dismissed | Planned | Production unavailability | 2024-07-12T15:25:52+01:00 | 2024-07-09T10:00:00+01:00 | 2024-08-12T18:00:00+01:00 | MW | 112 | 0 | 112 | Foreseen Maintenance | Grid |
Wind Onshore | 10YGB----------A |
T_VKNGW-4 | 48W00000VKNGW-4Z | Viking Energy Wind Farm LLP |
48X000000000314Y | 0000000000000000000009208_011 | Dismissed | Planned | Production unavailability | 2024-07-12T13:11:12+01:00 | 2024-07-09T10:00:00+01:00 | 2024-08-12T16:00:00+01:00 | MW | 112 | 0 | 112 | Foreseen Maintenance | Grid |
Wind Onshore | 10YGB----------A |
T_VKNGW-4 | 48W00000VKNGW-4Z | Viking Energy Wind Farm LLP |
48X000000000314Y | 0000000000000000000009208_010 | Dismissed | Planned | Production unavailability | 2024-07-12T10:22:51+01:00 | 2024-07-09T10:00:00+01:00 | 2024-08-12T14:00:00+01:00 | MW | 112 | 0 | 112 | Foreseen Maintenance | Grid |
Wind Onshore | 10YGB----------A |
T_VKNGW-4 | 48W00000VKNGW-4Z | Viking Energy Wind Farm LLP |
48X000000000314Y | 0000000000000000000009208_009 | Dismissed | Planned | Production unavailability | 2024-07-12T08:59:03+01:00 | 2024-07-09T10:00:00+01:00 | 2024-08-12T12:00:00+01:00 | MW | 112 | 0 | 112 | Foreseen Maintenance | Grid |
Wind Onshore | 10YGB----------A |