Affected Unit | Affected Unit EIC Code | Market Participant | Market Participant Code | Message ID | Event Status | Type Of Unavailability | Type Of Event | Publication Date | Event Start | Event Stop | Unit of Measurement | Unavailable Capacity | Available Capacity | Installed Capacity | Reason Of Unavailability | Remarks | Fuel Type | Bidding Zone |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
< 31 32 33 34 35 > | ||||||||||||||||||
T_VKNGW-1 | 48W00000VKNGW-14 | Viking Energy Wind Farm LLP |
48X000000000314Y | 0000000000000000000009205_001 | Dismissed | Planned | Production unavailability | 2024-07-03T07:58:49+01:00 | 2024-07-08T18:00:00+01:00 | 2024-07-11T17:00:00+01:00 | MW | 112 | 0 | 112 | Foreseen Maintenance | Grid |
Wind Onshore | 10YGB----------A |
T_VKNGW-2 | 48W00000VKNGW-22 | Viking Energy Wind Farm LLP |
48X000000000314Y | 0000000000000000000009206_001 | Dismissed | Planned | Production unavailability | 2024-07-03T07:59:53+01:00 | 2024-07-08T18:00:00+01:00 | 2024-07-11T17:00:00+01:00 | MW | 112 | 0 | 112 | Foreseen Maintenance | Grid |
Wind Onshore | 10YGB----------A |
T_VKNGW-3 | 48W00000VKNGW-30 | Viking Energy Wind Farm LLP |
48X000000000314Y | 0000000000000000000009207_001 | Dismissed | Planned | Production unavailability | 2024-07-03T08:01:09+01:00 | 2024-07-08T18:00:00+01:00 | 2024-07-11T17:00:00+01:00 | MW | 108 | 0 | 108 | Foreseen Maintenance | Grid |
Wind Onshore | 10YGB----------A |
T_MEDP-1 | 48W000000MEDP-12 | MEDWAY POWER LTD |
48X000000000076O | 0000000000000000000006040_010 | Inactive | Planned | Production unavailability | 2024-07-12T13:02:32+01:00 | 2024-06-06T23:00:00+01:00 | 2024-07-12T12:00:00+01:00 | MW | 710 | 0 | 710 | Foreseen Maintenance | Planned Outage |
Fossil Gas | 10YGB----------A |
T_MEDP-1 | 48W000000MEDP-12 | MEDWAY POWER LTD |
48X000000000076O | 0000000000000000000006040_009 | Dismissed | Planned | Production unavailability | 2024-01-23T15:17:17+00:00 | 2024-06-06T23:00:00+01:00 | 2024-07-12T12:00:00+01:00 | MW | 710 | 0 | 710 | Foreseen Maintenance | Planned Outage |
Fossil Gas | 10YGB----------A |
T_MEDP-1 | 48W000000MEDP-12 | MEDWAY POWER LTD |
48X000000000076O | 0000000000000000000006040_008 | Dismissed | Planned | Production unavailability | 2023-12-18T11:00:04+00:00 | 2024-06-06T23:00:00+01:00 | 2024-08-01T12:00:00+01:00 | MW | 710 | 0 | 710 | Foreseen Maintenance | Planned Outage |
Fossil Gas | 10YGB----------A |
T_MEDP-1 | 48W000000MEDP-12 | MEDWAY POWER LTD |
48X000000000076O | 0000000000000000000006040_007 | Dismissed | Planned | Production unavailability | 2023-10-20T18:08:11+01:00 | 2024-06-08T23:00:00+01:00 | 2024-08-03T12:00:00+01:00 | MW | 710 | 0 | 710 | Foreseen Maintenance | Planned Outage |
Fossil Gas | 10YGB----------A |
T_MEDP-1 | 48W000000MEDP-12 | MEDWAY POWER LTD |
48X000000000076O | 0000000000000000000006040_006 | Dismissed | Planned | Production unavailability | 2023-08-09T12:00:28+01:00 | 2024-06-06T23:00:00+01:00 | 2024-07-18T12:00:00+01:00 | MW | 710 | 0 | 710 | Foreseen Maintenance | Planned Outage |
Fossil Gas | 10YGB----------A |
T_MEDP-1 | 48W000000MEDP-12 | MEDWAY POWER LTD |
48X000000000076O | 0000000000000000000006040_005 | Dismissed | Planned | Production unavailability | 2022-11-21T12:41:29+00:00 | 2024-06-06T23:00:00+01:00 | 2024-06-28T12:00:00+01:00 | MW | 710 | 0 | 710 | Foreseen Maintenance | Planned Outage |
Fossil Gas | 10YGB----------A |
T_MEDP-1 | 48W000000MEDP-12 | MEDWAY POWER LTD |
48X000000000076O | 0000000000000000000006040_004 | Dismissed | Planned | Production unavailability | 2022-10-26T16:36:29+01:00 | 2024-06-07T23:00:00+01:00 | 2024-06-29T12:00:00+01:00 | MW | 710 | 0 | 710 | Foreseen Maintenance | Planned Outage |
Fossil Gas | 10YGB----------A |
T_MEDP-1 | 48W000000MEDP-12 | MEDWAY POWER LTD |
48X000000000076O | 0000000000000000000006040_003 | Dismissed | Planned | Production unavailability | 2022-08-05T15:14:33+01:00 | 2024-06-07T23:00:00+01:00 | 2024-06-17T12:00:00+01:00 | MW | 710 | 0 | 710 | Foreseen Maintenance | Planned Outage |
Fossil Gas | 10YGB----------A |
T_MEDP-1 | 48W000000MEDP-12 | MEDWAY POWER LTD |
48X000000000076O | 0000000000000000000006040_002 | Dismissed | Planned | Production unavailability | 2022-03-23T10:54:49+00:00 | 2024-06-07T23:00:00+01:00 | 2024-06-17T12:00:00+01:00 | MW | 710 | 0 | 710 | Foreseen Maintenance | Planned Outage |
Fossil Gas | 10YGB----------A |
T_GLNDO-1 | 48W00000GLNDO-1G | SSE GENERATION |
48X000000000077M | 0000000000000000000009239_002 | Inactive | Planned | Production unavailability | 2024-07-12T13:02:32+01:00 | 2024-07-12T10:00:00+01:00 | 2024-07-12T12:00:00+01:00 | MW | 0 | 100 | 100 | Foreseen Maintenance | Testing |
Hydro Water Reservoir | 10YGB----------A |
T_MEDP-1 | 48W000000MEDP-12 | MEDWAY POWER LTD |
48X000000000076O | 0000000000000000000006040_001 | Dismissed | Planned | Production unavailability | 2021-05-11T11:49:34+01:00 | 2024-06-07T23:00:00+01:00 | 2024-06-17T12:00:00+01:00 | MW | 710 | 0 | 710 | Foreseen Maintenance | Planned Outage |
Fossil Gas | 10YGB----------A |
T_GLNDO-1 | 48W00000GLNDO-1G | SSE GENERATION |
48X000000000077M | 0000000000000000000009239_001 | Dismissed | Planned | Production unavailability | 2024-07-11T16:05:04+01:00 | 2024-07-12T10:00:00+01:00 | 2024-07-12T12:00:00+01:00 | MW | 0 | 100 | 100 | Foreseen Maintenance | Testing |
Hydro Water Reservoir | 10YGB----------A |
T_GLNDO-1 | 48W00000GLNDO-1G | SSE GENERATION |
48X000000000077M | 0000000000000000000009033_003 | Inactive | Planned | Production unavailability | 2024-07-12T11:02:32+01:00 | 2024-07-01T08:00:00+01:00 | 2024-07-12T10:00:00+01:00 | MW | 100 | 0 | 100 | Foreseen Maintenance | Planned Outage |
Hydro Water Reservoir | 10YGB----------A |
T_GLNDO-1 | 48W00000GLNDO-1G | SSE GENERATION |
48X000000000077M | 0000000000000000000009033_002 | Dismissed | Planned | Production unavailability | 2024-07-11T16:03:46+01:00 | 2024-07-01T08:00:00+01:00 | 2024-07-12T10:00:00+01:00 | MW | 100 | 0 | 100 | Foreseen Maintenance | Planned Outage |
Hydro Water Reservoir | 10YGB----------A |
T_GLNDO-1 | 48W00000GLNDO-1G | SSE GENERATION |
48X000000000077M | 0000000000000000000009033_001 | Dismissed | Planned | Production unavailability | 2024-04-19T10:31:15+01:00 | 2024-07-01T08:00:00+01:00 | 2024-07-12T17:00:00+01:00 | MW | 100 | 0 | 100 | Foreseen Maintenance | Planned Outage |
Hydro Water Reservoir | 10YGB----------A |
T_FOYE-1 | 48W000000FOYE-14 | SSE GENERATION |
48X000000000077M | 0000000000000000000009238_005 | Inactive | Planned | Consumption unavailability | 2024-07-11T15:02:32+01:00 | 2024-07-10T14:15:00+01:00 | 2024-07-11T14:00:00+01:00 | MW | 150 | 0 | 150 | Shutdown | Water Management |
Hydro Pumped Storage | 10YGB----------A |
T_FOYE-1 | 48W000000FOYE-14 | SSE GENERATION |
48X000000000077M | 0000000000000000000009238_004 | Dismissed | Planned | Consumption unavailability | 2024-07-11T11:39:54+01:00 | 2024-07-10T14:15:00+01:00 | 2024-07-11T14:00:00+01:00 | MW | 150 | 0 | 150 | Shutdown | Water Management |
Hydro Pumped Storage | 10YGB----------A |
T_FOYE-1 | 48W000000FOYE-14 | SSE GENERATION |
48X000000000077M | 0000000000000000000009238_003 | Dismissed | Planned | Consumption unavailability | 2024-07-11T09:13:23+01:00 | 2024-07-10T14:15:00+01:00 | 2024-07-11T12:00:00+01:00 | MW | 150 | 0 | 150 | Shutdown | Water Management |
Hydro Pumped Storage | 10YGB----------A |
T_FOYE-1 | 48W000000FOYE-14 | SSE GENERATION |
48X000000000077M | 0000000000000000000009238_002 | Dismissed | Planned | Consumption unavailability | 2024-07-10T22:25:57+01:00 | 2024-07-10T14:15:00+01:00 | 2024-07-11T10:00:00+01:00 | MW | 150 | 0 | 150 | Shutdown | Water Management |
Hydro Pumped Storage | 10YGB----------A |
T_FOYE-1 | 48W000000FOYE-14 | SSE GENERATION |
48X000000000077M | 0000000000000000000009238_001 | Dismissed | Planned | Consumption unavailability | 2024-07-10T14:00:19+01:00 | 2024-07-10T14:15:00+01:00 | 2024-07-10T23:59:00+01:00 | MW | 150 | 0 | 150 | Shutdown | Water Management |
Hydro Pumped Storage | 10YGB----------A |
T_FOYE-2 | 48W000000FOYE-22 | SSE GENERATION |
48X000000000077M | 0000000000000000000009237_002 | Inactive | Planned | Consumption unavailability | 2024-07-11T01:02:32+01:00 | 2024-07-10T16:00:00+01:00 | 2024-07-10T23:59:00+01:00 | MW | 150 | 0 | 150 | Shutdown | Water Management |
Hydro Pumped Storage | 10YGB----------A |
T_FOYE-2 | 48W000000FOYE-22 | SSE GENERATION |
48X000000000077M | 0000000000000000000009237_001 | Dismissed | Planned | Consumption unavailability | 2024-07-10T13:57:43+01:00 | 2024-07-10T16:00:00+01:00 | 2024-07-10T23:59:00+01:00 | MW | 150 | 0 | 150 | Shutdown | Water Management |
Hydro Pumped Storage | 10YGB----------A |
T_FOYE-1 | 48W000000FOYE-14 | SSE GENERATION |
48X000000000077M | 0000000000000000000009236_003 | Inactive | Unplanned | Consumption unavailability | 2024-07-10T00:32:32+01:00 | 2024-07-09T22:39:00+01:00 | 2024-07-09T23:30:00+01:00 | MW | 150 | 0 | 150 | Failure | Plant Fault - Auxiliary Equipment |
Hydro Pumped Storage | 10YGB----------A |
T_FOYE-2 | 48W000000FOYE-22 | SSE GENERATION |
48X000000000077M | 0000000000000000000009235_002 | Inactive | Unplanned | Consumption unavailability | 2024-07-10T00:32:32+01:00 | 2024-07-09T22:39:00+01:00 | 2024-07-09T23:30:00+01:00 | MW | 150 | 0 | 150 | Failure | Plant Fault - Auxiliary Equipment |
Hydro Pumped Storage | 10YGB----------A |
T_FOYE-1 | 48W000000FOYE-14 | SSE GENERATION |
48X000000000077M | 0000000000000000000009236_002 | Dismissed | Unplanned | Consumption unavailability | 2024-07-09T22:58:59+01:00 | 2024-07-09T22:39:00+01:00 | 2024-07-09T23:30:00+01:00 | MW | 150 | 0 | 150 | Failure | Plant Fault - Auxiliary Equipment |
Hydro Pumped Storage | 10YGB----------A |
T_FOYE-1 | 48W000000FOYE-14 | SSE GENERATION |
48X000000000077M | 0000000000000000000009236_001 | Dismissed | Unplanned | Consumption unavailability | 2024-07-09T22:54:26+01:00 | 2024-07-09T22:39:00+01:00 | 2024-07-09T23:30:00+01:00 | MW | 0 | 150 | 150 | Failure | Plant Fault - Auxiliary Equipment |
Hydro Pumped Storage | 10YGB----------A |
T_FOYE-2 | 48W000000FOYE-22 | SSE GENERATION |
48X000000000077M | 0000000000000000000009235_001 | Dismissed | Unplanned | Consumption unavailability | 2024-07-09T22:52:01+01:00 | 2024-07-09T22:39:00+01:00 | 2024-07-09T23:30:00+01:00 | MW | 150 | 0 | 150 | Failure | Plant Fault - Auxiliary Equipment |
Hydro Pumped Storage | 10YGB----------A |
T_SGRWO-4 | 48W00000SGRWO-4F | Seagreen Wind Energy Ltd |
48X000000000263P | 0000000000000000000009094_005 | Inactive | Planned | Production unavailability | 2024-07-09T19:32:32+01:00 | 2024-07-06T07:00:00+01:00 | 2024-07-09T18:30:00+01:00 | MW | 140 | 0 | 140 | Foreseen Maintenance | Planned Outage |
Wind Offshore | 10YGB----------A |
T_SGRWO-3 | 48W00000SGRWO-3H | Seagreen Wind Energy Ltd |
48X000000000263P | 0000000000000000000009093_005 | Inactive | Planned | Production unavailability | 2024-07-09T19:32:32+01:00 | 2024-07-06T07:00:00+01:00 | 2024-07-09T18:30:00+01:00 | MW | 160 | 0 | 160 | Foreseen Maintenance | Planned Outage |
Wind Offshore | 10YGB----------A |
T_SGRWO-3 | 48W00000SGRWO-3H | Seagreen Wind Energy Ltd |
48X000000000263P | 0000000000000000000009093_004 | Dismissed | Planned | Production unavailability | 2024-07-09T15:27:41+01:00 | 2024-07-06T07:00:00+01:00 | 2024-07-09T18:30:00+01:00 | MW | 160 | 0 | 160 | Foreseen Maintenance | Planned Outage |
Wind Offshore | 10YGB----------A |
T_SGRWO-4 | 48W00000SGRWO-4F | Seagreen Wind Energy Ltd |
48X000000000263P | 0000000000000000000009094_004 | Dismissed | Planned | Production unavailability | 2024-07-09T15:28:27+01:00 | 2024-07-06T07:00:00+01:00 | 2024-07-09T18:30:00+01:00 | MW | 140 | 0 | 140 | Foreseen Maintenance | Planned Outage |
Wind Offshore | 10YGB----------A |
T_SGRWO-4 | 48W00000SGRWO-4F | Seagreen Wind Energy Ltd |
48X000000000263P | 0000000000000000000009094_003 | Dismissed | Planned | Production unavailability | 2024-07-03T21:35:54+01:00 | 2024-07-06T07:00:00+01:00 | 2024-07-10T19:00:00+01:00 | MW | 140 | 0 | 140 | Foreseen Maintenance | Planned Outage |
Wind Offshore | 10YGB----------A |
T_SGRWO-3 | 48W00000SGRWO-3H | Seagreen Wind Energy Ltd |
48X000000000263P | 0000000000000000000009093_003 | Dismissed | Planned | Production unavailability | 2024-07-03T21:34:57+01:00 | 2024-07-06T07:00:00+01:00 | 2024-07-10T19:00:00+01:00 | MW | 160 | 0 | 160 | Foreseen Maintenance | Planned Outage |
Wind Offshore | 10YGB----------A |
T_SGRWO-3 | 48W00000SGRWO-3H | Seagreen Wind Energy Ltd |
48X000000000263P | 0000000000000000000009093_002 | Dismissed | Planned | Production unavailability | 2024-05-29T15:52:33+01:00 | 2024-07-06T07:00:00+01:00 | 2024-07-11T19:00:00+01:00 | MW | 160 | 0 | 160 | Foreseen Maintenance | Planned Outage |
Wind Offshore | 10YGB----------A |
T_SGRWO-4 | 48W00000SGRWO-4F | Seagreen Wind Energy Ltd |
48X000000000263P | 0000000000000000000009094_002 | Dismissed | Planned | Production unavailability | 2024-05-29T15:53:41+01:00 | 2024-07-06T07:00:00+01:00 | 2024-07-11T19:00:00+01:00 | MW | 140 | 0 | 140 | Foreseen Maintenance | Planned Outage |
Wind Offshore | 10YGB----------A |
T_SGRWO-3 | 48W00000SGRWO-3H | Seagreen Wind Energy Ltd |
48X000000000263P | 0000000000000000000009093_001 | Dismissed | Planned | Production unavailability | 2024-05-20T17:13:47+01:00 | 2024-07-09T09:00:00+01:00 | 2024-07-12T17:00:00+01:00 | MW | 160 | 0 | 160 | Foreseen Maintenance | Planned Outage |
Wind Offshore | 10YGB----------A |
T_SGRWO-4 | 48W00000SGRWO-4F | Seagreen Wind Energy Ltd |
48X000000000263P | 0000000000000000000009094_001 | Dismissed | Planned | Production unavailability | 2024-05-20T17:17:28+01:00 | 2024-07-05T09:00:00+01:00 | 2024-07-08T17:00:00+01:00 | MW | 140 | 0 | 140 | Foreseen Maintenance | Planned Outage |
Wind Offshore | 10YGB----------A |
T_PEHE-1 | 48W000000PEHE-15 | SSE Thermal Generation (Scotland) Ltd |
48X0000000003024 | 0000000000000000000009123_007 | Inactive | Planned | Production unavailability | 2024-07-08T22:47:32+01:00 | 2024-07-02T23:00:00+01:00 | 2024-07-08T21:40:00+01:00 | MW | 180 | 1000 | 1180 | Foreseen Maintenance | Planned Outage |
Fossil Gas | 10YGB----------A |
T_PEHE-1 | 48W000000PEHE-15 | SSE Thermal Generation (Scotland) Ltd |
48X0000000003024 | 0000000000000000000009123_006 | Dismissed | Planned | Production unavailability | 2024-07-08T21:39:12+01:00 | 2024-07-02T23:00:00+01:00 | 2024-07-08T21:40:00+01:00 | MW | 180 | 1000 | 1180 | Foreseen Maintenance | Planned Outage |
Fossil Gas | 10YGB----------A |
T_PEHE-1 | 48W000000PEHE-15 | SSE Thermal Generation (Scotland) Ltd |
48X0000000003024 | 0000000000000000000009123_005 | Dismissed | Planned | Production unavailability | 2024-07-08T09:43:34+01:00 | 2024-07-02T23:00:00+01:00 | 2024-07-09T21:00:00+01:00 | MW | 180 | 1000 | 1180 | Foreseen Maintenance | Planned Outage |
Fossil Gas | 10YGB----------A |
T_PEHE-1 | 48W000000PEHE-15 | SSE Thermal Generation (Scotland) Ltd |
48X0000000003024 | 0000000000000000000009123_004 | Dismissed | Planned | Production unavailability | 2024-07-04T10:28:41+01:00 | 2024-07-02T23:00:00+01:00 | 2024-07-09T23:00:00+01:00 | MW | 180 | 1000 | 1180 | Foreseen Maintenance | Planned Outage |
Fossil Gas | 10YGB----------A |
T_PEHE-1 | 48W000000PEHE-15 | SSE Thermal Generation (Scotland) Ltd |
48X0000000003024 | 0000000000000000000009123_003 | Dismissed | Planned | Production unavailability | 2024-06-06T09:46:33+01:00 | 2024-07-02T23:00:00+01:00 | 2024-07-05T23:00:00+01:00 | MW | 180 | 1000 | 1180 | Foreseen Maintenance | Planned Outage |
Fossil Gas | 10YGB----------A |
T_PEHE-1 | 48W000000PEHE-15 | SSE Thermal Generation (Scotland) Ltd |
48X0000000003024 | 0000000000000000000009123_002 | Dismissed | Planned | Production unavailability | 2024-06-04T13:35:45+01:00 | 2024-06-10T08:00:00+01:00 | 2024-06-12T23:00:00+01:00 | MW | 780 | 400 | 1180 | Foreseen Maintenance | Planned Outage |
Fossil Gas | 10YGB----------A |
T_PEHE-1 | 48W000000PEHE-15 | SSE Thermal Generation (Scotland) Ltd |
48X0000000003024 | 0000000000000000000009123_001 | Dismissed | Planned | Production unavailability | 2024-05-29T12:06:53+01:00 | 2024-06-07T08:00:00+01:00 | 2024-06-09T23:00:00+01:00 | MW | 180 | 1000 | 1180 | Foreseen Maintenance | Planned Outage |
Fossil Gas | 10YGB----------A |
T_BEATO-3 | 48W00000BEATO-3P | Beatrice Offshore Windfarm Limited (BOWL) |
48X000000000208X | 0000000000000000000009180_005 | Inactive | Planned | Production unavailability | 2024-07-08T19:02:32+01:00 | 2024-07-08T11:00:00+01:00 | 2024-07-08T18:00:00+01:00 | MW | 168 | 0 | 168 | Foreseen Maintenance | Planned Outage |
Wind Offshore | 10YGB----------A |
T_BEATO-4 | 48W00000BEATO-4N | Beatrice Offshore Windfarm Limited (BOWL) |
48X000000000208X | 0000000000000000000009181_005 | Inactive | Planned | Production unavailability | 2024-07-08T19:02:32+01:00 | 2024-07-08T11:00:00+01:00 | 2024-07-08T18:00:00+01:00 | MW | 168 | 0 | 168 | Foreseen Maintenance | Planned Outage |
Wind Offshore | 10YGB----------A |
T_BEATO-1 | 48W00000BEATO-1T | Beatrice Offshore Windfarm Limited (BOWL) |
48X000000000208X | 0000000000000000000009178_005 | Inactive | Planned | Production unavailability | 2024-07-08T19:02:32+01:00 | 2024-07-08T11:00:00+01:00 | 2024-07-08T18:00:00+01:00 | MW | 126 | 0 | 126 | Foreseen Maintenance | Planned Outage |
Wind Offshore | 10YGB----------A |